Equestrial Exhibit Structure
Discover the Equestrial Exhibit Structure by Hard Bakka Rigging. 94 tonnes expertly lifted in 12 days using a 30t crane and boom lifts—completed on…
Mining Sorting Structure – Townsville
Hard Bakka Rigging successfully assembled the Mining Sorting Structure in Townsville’s Queensland gold mines. With innovative methods and strict attention to detail, components like…
TfNSW Facility Upgrade – Yennora
Hard Bakka Rigging successfully completed the steel installation for TfNSW’s Yennora Facility Upgrade, supporting advanced infrastructure for future transport systems.
Mining – Sorting Machine Structure
Hard Bakka Rigging pre-assembled the SLN Mining Sorting Machine Structure in Parramatta for Tomra’s Open Day. With seamless precision and efficiency, the structure was…
Snowy Hydro 2.0
Hard Bakka Rigging’s EBA crew completed the installation of 7 structural steel structures for Snowy Hydro 2.0 at Kurri Kurri. The project was finished…
Putney Hills
Hard Bakka Rigging completed the Putney Hills project efficiently, managing 64 tonnes of steel in 90 days. Despite frequent design changes, the team ensured…
Coogee
Hard Bakka Rigging expertly completed the Coogee project, handling 18 tonnes of steel over 12 days using advanced equipment, with zero incidents and exceptional…
Carramar
Hard Bakka Rigging expertly delivered the 7-tonne Carramar project, ensuring precision, safety, and quality. Completed on time and on budget within 10 days, it…
Richmond
Hard Bakka Rigging completed the Richmond RAAF Refueling Shelter project, installing 36 tonnes of steelworks efficiently and to the highest compliance standards, supporting critical…
Fairfield East
Hard Bakka Rigging successfully completed the Fairfield East project, installing 24 tonnes of steel with expert rigging services, ensuring safety, precision, and timely delivery…