Back
Carpark Structures Education Infrastructure Steel Projects University Upgrades

Western Sydney University

Western Sydney University - Upgraded Carpark For 3 Campuses 

Multi-Campus Carpark Upgrade

Location: Western Sydney, NSW
Sector: Education Infrastructure
Project Scope: Structural steel works for upgraded carparks across 3 campuses
Duration: 5 Weeks
Crew Size: 4–6
Lifting Equipment Used: 30T Crane, Boom Lifts, Forklifts
Site Incidents Reported: Nil
Challenges Met: Multi-site coordination, tight delivery schedules, live campus environments


Project Overview

Hard Bakka Rigging was contracted to assist with the
structural steel erection for upgraded carpark facilities across three Western Sydney University campuses. This project aimed to expand and modernise parking infrastructure to accommodate increased student and staff capacity, while improving safety and accessibility standards across the campuses.

Each site required a tailored approach due to differing layouts, pedestrian flow considerations, and ongoing university operations. The scope included steel-framed carpark extensions, roof structures, and supporting access infrastructure—all delivered in tight timeframes during active semesters.


Multi-Campus Execution

Our crew worked across
three campuses simultaneously, coordinating with multiple construction teams to ensure deadlines were met without compromising safety or quality. The carparks were constructed using pre-fabricated steel components that required precise rigging and alignment, as well as efficient sequencing to avoid congestion in busy university areas.

Despite challenges posed by variable site conditions and strict access limitations, our team completed each steel structure on time and on budget. The use of a 30T crane, boom lifts, and telehandlers enabled seamless lifting and placement of heavy steel beams and roof structures.


Safety and Compliance

Operating within live university environments required stringent safety procedures. Our team underwent
Working With Children Checks and followed campus-specific safety protocols to mitigate risk to students and staff. Comprehensive site inductions, SWMS documentation, and real-time communication with stakeholders ensured smooth operations across all three sites.



This project is a testament to Hard Bakka Rigging’s ability to manage
multi-site logistics, deliver consistent quality, and maintain high safety standards across complex education infrastructure upgrades.


Discover the upgraded carparks created for three Western Sydney University campuses completed by Hard Bakka Rigging. Completed on time and on budget.

Leave a Reply

Your email address will not be published. Required fields are marked *