Western Sydney Airport – OCC Building

Western Sydney Airport – OCC Building

Structural Steel Erection for Airport Infrastructure

Hard Bakka Rigging erected the structural steel and purlins for Zones 1 and 2 of the Operations Control Centre (OCC) at Western Sydney International Airport. The package covered approximately 166.8 tonnes of structural steel and 5,405 lineal metres of purlins and girts, completed in 2025.

The OCC is the nerve centre of the airport, managing airfield lighting, ground movement, terminal systems and emergency response. Airport infrastructure runs on a strict programme and strict compliance requirements, so lift studies and staged erection planning came first. The steel went up in planned stages across both zones, with structural alignment checked as each stage was erected.

Quality control ran through the whole package. The OCC is CC2 structural steel, erected to AS 4100 and AS/NZS 5131, with QA checklists, ITPs and bolt verification recorded as erection progressed.

Key Highlights:

– Project Type: Airport Infrastructure

– Location: Western Sydney Airport, NSW

– Scope: Structural steel and purlin erection, Zones 1 & 2

– Structural Steel: Approx. 166.8 tonnes, CC2

– Purlins & Girts: Approx. 5,405 lm

– Equipment: 30T crane, boom lifts and forklifts

– Completed: 2025

The OCC project shows Hard Bakka Rigging’s capability to erect structural steel within a major airport infrastructure programme, combining lift planning, staged erection and documented QA.

Infrastructure steel package coming up? Send your drawings to sales@hardbakkarigging.com.au or call +61 415 878 744.

~166.8 tonnes of CC2 structural steel and 5,405 lm of purlins and girts for the OCC at Western Sydney Airport.

Leave a Reply

Your email address will not be published. Required fields are marked *